Client Overview:
- Client: Nikolay Tomov
- Location: 8 Bragato Place, Chatswood, Auckland 0626
- Scope: Crystalline waterproofing of a construction block, including surface preparation and the application of two coats of crystalline waterproofing products.
Project Summary:
iDry Restorations was tasked with applying a crystalline waterproofing system at a construction site in Chatswood, Auckland. The project involved grinding the concrete block to remove old coatings and contamination before applying two coats of crystalline waterproofing. The work was conducted under challenging conditions, with multiple contractors on site and a tight timeline. Dust control was a major concern, which was mitigated using grinders with dust coating systems.
Objectives:
- Surface Preparation: Grind the block to remove the existing coatings, contamination, and ensure a clean, prepared surface for the waterproofing application.
- Crystalline Waterproofing: Apply two coats of crystalline waterproofing products to protect the block from water ingress and contamination.
- Dust Management: Minimize dust and debris during the grinding process by using specialized dust control systems, ensuring minimal disruption to the ongoing work by other contractors.
Challenges:
- Active Construction Site: The site was busy with multiple contractors working simultaneously, which required careful coordination to avoid interruptions or delays.
- Tight Timeline: The project needed to be completed within a strict deadline as the site was in the final stages of construction, and delays could have impacted the overall project completion.
- Dust Control: Grinding old coatings from the block generated significant dust, which needed to be managed effectively to avoid contaminating the work of other contractors and ensure a clean surface for the waterproofing application.
Solution Implementation:
- Grinding and Dust Control: The team used specialized grinders equipped with dust coating systems to grind the concrete block and remove old coatings. This minimized dust on the construction site and allowed other contractors to continue working with minimal disruption.
- Crystalline Waterproofing Application: Two coats of high-performance crystalline waterproofing products were applied to the prepared surface. This ensured long-term protection of the block from water damage, making it suitable for the harsh conditions the site would face.
- Coordination with Contractors: The team worked closely with the site manager and other contractors to ensure the project timeline was adhered to without causing any delays to the overall construction process.
Client Interaction:
Nikolay Tomov, representing the client, was actively involved throughout the project. Regular updates were provided on the progress, and the team ensured transparency regarding the work being done. Payment milestones were promptly met, with the final balance settled upon project completion.
Results:
- Successful Surface Preparation: The old coatings and contaminants were successfully removed, and the surface was prepared for waterproofing without causing disruption to other ongoing work.
- Waterproofing Application: The two coats of crystalline waterproofing were applied smoothly, providing long-lasting protection against water ingress and ensuring the block’s durability in the future.
- Minimal Dust Impact: The use of dust control systems ensured that dust was kept to a minimum during the grinding process, reducing the impact on the other contractors working on-site.
Conclusion:
The crystalline waterproofing project at 8 Bragato Place, Chatswood, was successfully completed within a tight timeline, despite the challenges posed by the active construction site. iDry Restorations' use of dust control systems and precise coordination with other contractors ensured that the waterproofing work was completed efficiently and without disrupting the overall construction process. The application of two coats of crystalline waterproofing products provided the site with durable, long-lasting protection, meeting the client’s expectations.